|
||||
|
||||
|
Weston Mountain Ponds
PROJECT COMPLETION REPORT - OWEB GRANT #201-516 Grant Period: 3/3/02 to 6/30/04 Background: This project installed four small-scale infiltration ponds for the primary purpose of collecting and retaining water from surface flow, snow melt, and precipitation. This retained water should then saturate the ground and slowly seep into nearby Heifer, Rayborn, and Dry Creek Canyons, ultimately resulting in increased instream flow in Pine Creek during low-flow periods. Any additional water should benefit the downstream habitat for bull trout and steelhead (ESA-listed as threatened/endangered), as well as address issues delineated under the Clean Water Act. This is a demonstration project for utilizing small-scale infiltration ponds as a method of upland water storage and in-stream flow restoration. It is the intention of the Walla Walla Basin Watershed Council (WWBWC) to use these first ponds to encourage other landowners throughout the Walla Walla River watershed to install ponds to enhance stream flow during low flow periods. (Map of Project Area) The overall watershed benefits of this project should include:
Project Siting, Permitting and Design: 1. Greg Card (NRCS Engineer) had developed a checklist approach to pond design and permitting (NRCS Permitting Codes # 378, 410 and 638), as well as an operation and maintenance checklist and landowner agreement forms. These checklists were utilized in concert with site-specific designs developed and supervised by Bob Martin (NRCS Engineer-Retired) and our local NRCS staff (Cliff Harris - Pendleton Office). 2. Oregon Water Resources Department was consulted and a legal water right attained for each pond for water storage, wildlife, and watershed benefit (excluding stock watering). 3. Oregon Department of Fish and Wildlife, Oregon Department of State Lands were each consulted regarding wetland issues and permitting. 4. Oregon Department of Fish and Wildlife, United States Fish and Wildlife Service, United States Forest Service - Umatilla along with local NRCS staff were consulted regarding endangered species issues and permitting. 5. Umatilla County Planning was consulted for zone and other site permitting issues and permitting. 6. NRCS - Portland was consulted on Cultural Resource sites and issues. 7. Anderson Perry & Associates, Inc. was contracted to conduct soil proctor and nuclear densitometer testing to address dam construction concerns (NRCS/OWRD requirements). 8. Local and regional contractors were given site tours and bids were accepted for pond construction. 9. Umatilla Soil and Water Conservation Service and NRCS were consulted on site fencing costs and native planting issues. 10. Landowners were consulted throughout this entire process regarding pond locations, access issues, cost share, precipitation quantities, plantings, and all project elements. Tom Buell and Sally Wilson have been very helpful and enthusiastic about the project. Jim Burns also helped with site visits and promoted the project to other landowners. Project Survey and Construction: Fencing and seeding was done by landowners during the fall of 2003, and finished during the early summer of 2004. Fencing materials, labor, NRCS-approved seed, and some wetland plants were furnished by the landowners as cost share for the project. The landowners will continue to manage their sites for weeds, fence repairs and additional native grass seeding. Preliminary Results: The primary goal of the Weston Mountain Ponds project is to slow runoff and thereby increase low season flow. However, quantifying water seepage from the ponds moving down gradient to increase flow volumes in ephemeral streams is a difficult task. WWBWC staff attempted to quantify a before and after change in the down-gradient water table using a mini-piezometer at one pond location. Unfortunately, both the before and after-construction results showed "dry" or "no static level recorded" conditions at the site. More promising results were found at one pond location where an abandoned cistern was located about ten feet from the dam of the new pond. Cisterns historically were used to develop low-flow springs or streams for domestic and livestock uses. During the construction of this particular pond (summer 2003), the cistern was noted to be dry. Late during the following summer (2004), with the pond still full of water, standing water was noted in the cistern. Additional evidence of slower water seepage can be seen in some of the photo monitoring conducted by WWBWC. Photos were then taken at set points throughout the project to capture comparisons at each pond site for the different stages and seasons of the project. While it is difficult to see in some pictures, the zone below the ponds has shown a marked improvement in greener riparian vegetation and increased wetness, evidence that water is seeping slowly from the pond into the streambed. Photo monitoring will continue in order to track long-term changes in riparian condition and vegetation. Other indicators of habitat restoration success are the ample presence of waterfowl, frogs and toads noted on monthly monitoring visits. Terrestrial animal tracks have also been seen, demonstrating the ponds are being used by wild turkeys, deer, elk, coyote, bear, and other mammals as high altitude water refuge. Monitoring will continue and five follow-up annual reports will be sent to OWEB. From a pure water budget perspective, the benefits of the project are quite clear: 5.2 acre-feet of water that normally would have drained out of the Walla Walla basin during the spring freshet was still contained in the upper headwaters during the hottest, driest months of the water year. When comparing the benefits to wildlife, sediment control, esthetics and perceived down-gradient riparian improvement, this project can be considered a success. The Feasibility Study being conducted by the Army Corps of Engineers (USACE) and the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) has shown that large-scale water storage options will be very costly for the Walla Walla basin's small community with issues from seismic-dam failure concerns to multi-million dollar price tags. When considering water storage options, small scale infiltration ponds should be considered a viable alternative. The ponds have enhanced the properties of the landowners and increased their knowledge of WWBWC's other projects and efforts. It has introduced WWBWC staff to many types of permitting and helped us develop relationships with other agencies and contractors, as various new services were required. We look forward now to working with other landowners to complete similar projects that will increase low-season flows to an easily measurable amount. Changes to the Original Proposal: Lessons learned from the Project and
Recommendations for Similar Projects: |
||||
|
The WWBWC is a 501(c)(3) non-profit Donations are welcomed to support efforts and are tax-deductible as allowed by law
|
Home Page • Projects • Maps & Data • Funding Sources Media • Education • Contact Us • Directions to the Office
|
|||
|
|
|
|||